Penerapan Metode Line Of Balance (LoB) pada Penjadwalan Proyek Perumahan

Authors

  • Yeghal Sahadutha Universitas Kristen Indonesia Paulus Author
  • Josefine Ernestine Latupeirissa Universitas Kristen Indonesia Paulus Author
  • Ari Kusuma Universitas Kristen Indonesia Paulus Author

DOI:

https://doi.org/10.52722/stvdtv47

Keywords:

Construction, Line of Balance, Project scheduling

Abstract

Scheduling in project implementation is very important to determine the work properly and correctly, therefore the construction of a project cannot be separated from scheduling in increasing project success. In houtilizing construction projects there is work that is done repeatedly or work with repetitive properties. The goal of this study is to compute the timing of the work of each unit of work. To get the outcomes of the timing of work in this study utilizing the Line of Balance (LoB) technique. This study is performed by field observation and calculating the timing of work from the volume value of each work unit. Based on the outcomes of the analysis performed for scheduling the project type 70/90 as many as 22 units, namely 1165 days or 3.2 years. This technique is effective because it displays production levels and time information in a graphical format so that it can figure out errors that happen.

Downloads

Download data is not yet available.

References

[1] Wildan Firdaus dan Budi Witjaksana, “Analisis Pengendalian Waktu Proyek dengan Metode Line Of Balance (LoB) pada Proyek Perumahan Central Park Middle East Ring Road,” J. Sci. Res. Dev., vol. 5, no. 2, hlm. 851–865, Jan 2024, doi: 10.56670/jsrd.v5i2.263.

[2] W. Sudarson, “Evaluasi Penjadwalan Proyek dengan Metode Line of Balance (Studi Kasus: Hotel Santika Batam),” J. Civ. Eng. Plan., vol. 1, no. 2, hlm. 85, Des 2020, doi: 10.37253/jcep.v1i2.715.

[3] F. Supriani, “Analisis Penjadwalan Proyek pada Pekerjaan Repetitif dengan Metode Line of Balance dan Precefence Diagram Method,” Teknosia, vol. 16, no. 2, hlm. 9–19, Jan 2023, doi: 10.33369/teknosia.v16i2.23648.

[4] S. M. Kalia, A. Utiarahman, dan M. Y. Tuloli, “Penerapan Metode Line of Balance pada Proyek Konstruksi Repetitif (Studi Kasus: Perumahan GriyaTunas Mandiri),” J. Penelit. Jalan Dan Jemb., vol. 2, no. 2, Okt 2022, doi: 10.59900/ptrkjj.v2i2.85.

[5] R. Sinaga, P. Simanjuntak, dan Setiyadi, “Analisis dan Penerapan Metode Line of Balance pada Proyek Repetitif,” J. Rekayasa Tek. Sipil Dan Lingkung. - CENTECH, vol. 2, no. 2, hlm. 82–89, Nov 2021, doi: 10.33541/cen.v2i2.3466.

[6] S. Widodo, “Analisis Penjadwalan Proyek Dengan Metode Line of Balance Pada Proyek Pembangunan Perumahan Grand Efata Malibela,” J. Tek. Sipil Ranc. Bangun, vol. 8, no. 1, hlm. 115–123, Apr 2022, doi: 10.33506/rb.v8i1.1736.

[7] A. Maddeppungeng, A. Budiman, dan G. Christopher, “Metode Keseimbangan Garis pada Penjadwalan Proyek Repetitif ,” Konstruksia, vol. 14, no. 1, hlm. 88, Des 2022, doi: 10.24853/jk.14.1.88-106.

[8] I. K. Alit Astrawan Putra, I. W. Diasa, N. K. Sri Astati Sukawati, I. G. N. Eka Partama, dan I. M. Yogi Antara Putra, “Perbandingan Metode Penjadwalan Line of Balance (LoB) Dengan Precedence Diagram Method (PDM) Pada Proyek Kontruksi Repetitif (Studi Kasus: Proyek Pembangunan Struktur Villa Cemongkak Pecatu Kabupaten Badung),” J. Ilm. Vastuwidya, vol. 6, no. 1, hlm. 9–24, Feb 2023, doi: 10.47532/jiv.v6i1.771.

[9] Silvianita, "A Comparison of Application of The Project Schedulling Using Precedence Diagram Method and Line of Balance and Position Weight Method to Construct Circulating Close Cooling Water System," IAME Publication, vol.9, no.13, 2020.

[10] I. W. Y. Astawa, N. K. T. Tastrawati, dan L. P. I. Harini, “Waktu Penyelesaian Proyek Konstruksi Menggunakan Precedence Diagram Method dan Line of Balance,” E-J. Mat., vol. 9, no. 3, hlm. 190, Sep 2020, doi: 10.24843/MTK.2020.v09.i03.p298.

[11] O. Gondokusumo dan S. A. Lythio, “Penerapan Line of Balance dengan Target Waktu Penyelesaian Proyek untuk Optimasi Penjadwalan Proyek Rumah Tinggal,” JMTS J. Mitra Tek. Sipil, hlm. 845–856, Nov 2022, doi: 10.24912/jmts.v5i4.20607.

[12] A. P. A. Putra dan G. Sarya, “Analisis Penjadwalan dan Alokasi Biaya Menggunakan Metode Line of Balance pada Proyek Jalan dan Jembatan Frontage Road Waru-Buduran,” J. Kacapuri J. Keilmuan Tek. Sipil, vol. 5, no. 1, hlm. 390, Jun 2022, doi: 10.31602/jk.v5i1.7568.

[13] C. W. Ningrum dan M. Beatrix, “Mempercepat Waktu Pelaksanaan Proyek Pembangunan Jalur Ganda Kereta Api Antara Mojokerto-Sepanjang Melalui Penjadwalan Line of Balance,” J. Manaj. Teknol. Tek. Sipil, vol. 5, no. 2, hlm. 277–289, Jan 2023, doi: 10.30737/jurmateks.v5i2.4020.

[14] N. Soplanit, N. Maelissa, dan H. D. Titaley, “Analisis Penerapan Metode Line of Balance pada Pembangunan Rumah Susun PemKab Kepulauan Tanimbar,” J. SIMETRIK, vol. 11, no. 2, hlm. 474–479, Jan 2022, doi: 10.31959/js.v11i2.773.

[15] H. Sarjono, I. Patria, A. Sudjatmoko, dan D. Safitri, “Analisis Kegiatan Paket Wisata Sekolah Dengan Metode Line Of Balance Pada Industri Pariwisata,” J. Ecogen, vol. 6, no. 1, hlm. 1, Apr 2023, doi: 10.24036/jmpe.v6i1.14409.

Downloads

Published

2025-09-23

How to Cite

[1]
Y. Sahadutha, J. E. Latupeirissa, and A. Kusuma, “Penerapan Metode Line Of Balance (LoB) pada Penjadwalan Proyek Perumahan”, PCEJ, vol. 7, no. 3, pp. 419–424, Sep. 2025, doi: 10.52722/stvdtv47.